SunTrax Oval Track Construction
Service
SunTrax Test Facility Project Phase 1
Service(s) Provided
CEI
Client
Florida’s Turnpike Enterprise (FTE)
Project Dates
2017 – 2019
Budget/Cost
$42 Million
This project involved constructing a 2.25-mile oval track designed to support high-speed testing of emerging toll technologies, intelligent transportation systems (ITS), and automated and connected vehicles. The track features a five-lane straightaway with paved shoulders and two-lane, superelevated oval curves with paved shoulders.
The project also included approximately one million cubic yards of earthwork, two 30-foot-high mechanically stabilized earth (MSE) retaining walls, more than 16,600 linear feet of drainage pipe, 91 drainage structures, and two wet detention ponds. Additional features included a three-sided precast arch bridge culvert on a mass concrete spread footing foundation spanning 56 feet; an individually dimmable highway lighting system; and ITS elements, including more than 38,500 linear feet of fiber-optic cable and 12 closed-circuit television (CCTV) cameras.
The project also included an 11,784-square-foot Operations Building and a 9,074-square-foot Storage Building. Both buildings met the Silver-level requirements for Leadership in Energy and Environmental Design (LEED), as established by the U.S. Green Building Council (USGBC).
The project received the 2019 Florida Transportation Builders’ Association (FTBA) Best in Construction Award for Project of Special Significance, the 2019 Engineering News-Record (ENR) Award of Merit for Specialty Construction, and the 2020 America’s Transportation Awards (SASHTO) award for Best Use of Technology and Innovation.





