Wekiva 8

SR 429 (Wekiva Pkwy Section 8) Systems Interchange at I-4 Design-Build Project

Service(s) Provided

CEI

Client

FDOT District 5

Project Dates

2018 – 2024

Budget/Cost

$253.3 Million

This design-build project created a system-to-system interchange connecting SR 429, I-4, and SR 417. The project included constructing 2.6 miles of the SR 429 limited-access toll road, completing the final segment of the Wekiva Parkway, and widening and reconstructing two miles of I-4 to accommodate the future I-4 Beyond the Ultimate (BtU) Project. Work also expanded the SR 417 interchange at International Parkway to a full interchange.

The project included 22 new bridges, including third-level flyovers, and a toll gantry spanning the northbound and southbound travel lanes. Additional improvements included widening two existing bridges and constructing 12 new multi-span bridges and eight new single-span bridges.

Key features included nearly nine miles of mechanically stabilized earth (MSE) walls; more than 108,000 linear feet of drainage pipe and 600 drainage structures supporting stormwater management and floodplain compensation (FPC) systems; more than four million cubic yards of earthwork, including nearly two million cubic yards of imported fill; 3.6 miles of sound walls; highway and high-mast lighting; new intelligent transportation systems (ITS) components throughout the project limits; more than 700 sign structures; provisions for landscaping; demolition of existing bridges; and pavement markings.

Scroll to Top