U.S. 41 Arterial F.R.A.M.E. Systems Manager Project
Service
U.S. 41 Arterial F.R.A.M.E. Systems Manager Project
Service(s) Provided
Technology
Client
FDOT District 1
Project Dates
July 2019 – December 2019
Budget/Cost
$168 Thousand
As a task work order under Metric’s DW Traffic Operations ITS Consultant contract, this project was part of Florida’s Regional Advanced Mobility Elements (F.R.A.M.E.) program and involved deploying connected vehicle (CV) and automated safety applications along 34 miles of the U.S. 41 corridor in Lee County, spanning 71 traffic signals from south of Woods Edge Parkway to north of Lake Fairways Boulevard.
The project supported the Florida Department of Transportation (FDOT) District 1 goal of improving safety and mobility along U.S. 41, which runs parallel to I-75 and serves as a detour route during incident management. Metric applied a Systems Manager approach to design and implementation, ensuring consistency and seamless integration with FDOT District 1 and Lee County systems.
The project team evaluated connections between CV technologies, supplemental applications, Lee County’s advanced traffic management system (ATMS), and FDOT District 1’s SunGuide® system. Work included evaluating optimal roadside unit (RSU) locations and assessing the integration and compatibility of applications such as Signal Phase and Timing (SPaT) and passive pedestrian protection. Metric also recommended infrastructure upgrades, including switches, firewalls, servers, cellular modems, edge computing devices, and traffic signal controllers, to support CV technology.
Additional responsibilities included identifying MAP message requirements and other applicable CV applications, defining hardware and software security requirements, updating the Regional Intelligent Transportation System Architecture (RITSA), and developing a Concept of Operations (ConOps), System Validation Plan (SV), Systems Engineering Management Plan (SEMP), high-level cost estimates, and CV equipment procurement analysis.
Stakeholder coordination was a key component of the project. Metric provided similar services for the U.S. 98 Connected Vehicle Pilot Project, which involved testing at four intersections. Findings from that pilot informed the U.S. 41 F.R.A.M.E. deployment.