DMS Replacement Project

DMS Replacement Project

Service(s) Provided

ITS CEI

Client

Central Florida Expressway (CFX)

Project Dates

8/2020 - Present

Construction Budget

$5,949,106.04

CEI Budget

$491,682.26

This project consists of providing all labor, materials, equipment and incidentals necessary to transport, install, test, and successfully replace fourteen (14) 3 Line DMS signs along the SR 429, 414, 451, 453, 408, 528 and 520 corridors. These locations include installing backup LP generator systems and integration into nearby toll plazas to tie into the generator backup systems. Infrastructure for the deployment of portable generators is included at various DMS locations throughout the system. The project includes the development of an electrical microgrid system for the SR 528 corridor which will install multiple LP Generator systems at the electrical point of services to provide all corridor devices redundant power supply.

Scroll to Top